Design & planning

Project Management & Main Contractor

One contract, one contact and one person accountable, instead of five trades and a homeowner in the middle.

The rear of a house part way through a two storey extension, the dark clad upper storey complete above a cream rendered ground floor that has been opened out beneath a concrete lintel with short stubs of wall left at each end, the removed white doors stood against the wall alongside, tools and rubble across wet dark decking Fig. 01

Most of what goes wrong on an extension is not bad building. It is five separate parties each holding one piece of the job, a homeowner in the middle holding none of them, and nobody whose problem it is when the pieces fail to line up. This page explains how we take that off you, and what to ask anybody else who says they will.

Project Management & Main Contractor in the Colchester area
Fig. 01
Chapter 01

What actually goes wrong on an extension

It is rarely the brickwork. It is the gaps between the people doing the work.

The stories people tell about extensions are almost never about a wall built out of plumb. They are about a steel ordered before the calculations arrived and turning out to be the wrong section. A window supplier who measured an opening that then changed. Drawings showing a drain in a position the survey contradicts. Building Control asking at inspection for something nobody had priced. A plasterer booked for a Monday who could not start because the electrician overran, and who was then unavailable for three weeks.

Each of those is small on its own. Together they are the months and the thousands. And they share one cause: none of them is anybody’s job. The designer’s responsibility ends at the drawing. The engineer’s ends at the calculation. The window supplier’s begins at a survey of an opening that has to exist already. The builder’s begins when there is something to build. Between each of those is a joint, and joints are where jobs leak.

The homeowner is the only person present at every stage, so by default the joints become theirs. Worse, they are technical joints. Is the beam the right one. Is the ventilation detail adequate. Is the plasterer right that the boards should have been thicker. Those are arbitrations between professionals, and you are being asked to make them with no way of assessing either answer.

Chapter 02

The usual arrangement, and how you end up in the middle

Four appointments, four contracts with you, and no contract at all between the people who have to agree.

The standard route goes like this. You find someone to draw it. They recommend an engineer, or you find one. You take the drawings to two or three builders for prices. Then, to save money, you appoint some trades directly: the electrician a friend used, the kitchen company, the window supplier who quoted at a show. Everybody has a contract with you. Nobody has a contract with anybody else.

That works perfectly while everything goes to plan. Its flaw is that it contains no mechanism for disagreement. When the window company says the opening is wrong, the builder says the drawing was wrong and the technician says it was built wrong, all three are correct within their own frame, all three are owed money by you, and none of them owes anything to the others. You are now the arbitrator, and the evidence is technical.

The cost is rarely the argument itself. It is the four weeks the job stands still while it happens, and the trades who take other work in the meantime and are not available when it resolves. There is also a version that looks like our arrangement but is not: a builder who prices the build only and tells you to sort the drawings and the engineer out yourself. It sounds reasonable. It leaves the two decisions that constrain everything downstream outside the contract.

Instrument 01

Will you need planning permission?

Four questions, an honest answer, and nothing sent anywhere. This runs entirely in your browser.

What are you extending?

Permitted development rights for extensions apply to houses. Flats and maisonettes are a different route entirely.

Is the property listed?

Listed building consent is a separate decision from planning permission, and work without it is a criminal offence rather than a planning irregularity.

Has the house been extended before?

Depth is measured from the ORIGINAL rear wall, so a previous owner's extension has already used part of your allowance. This catches almost everybody.

Is it in a conservation area?

Colchester has a number of them, including the historic core, the Dutch Quarter, part of Lexden and several village centres. The boundaries rarely follow the roads you would expect.

Indication only

Answer the four questions for an indication

Whatever the answer, Building Regulations approval is always needed. We check the planning history, the designation and the deeds on your address before anyone draws anything, because it decides the design rather than the other way round.

This is an indication based on four questions, not advice on your property. Planning rules change and the position depends on your specific address, its planning history and its designation.

Project Management & Main Contractor in the Colchester area
Fig. 03
Chapter 03

What main contractor actually means

One party holds the contract for the whole job, and carries the whole job.

Main contractor is a contractual description rather than a marketing word. It means one party enters into a single contract with you covering the entire works, then sub-contracts the parts of it that need specialists. The people doing the sub-contracted work are contracted to us, not to you. You have one agreement, one price and one person to hold to it.

Three things follow. Responsibility is single: if water gets in at the junction, it does not matter to you whether the roofer or the bricklayer caused it, because both are ours. Co-ordination sits inside the price rather than being done by you for nothing in the evenings. And sequencing risk transfers: if a trade overruns, reorganising the following six weeks is our problem, not a series of phone calls you make from work.

Since October 2023 the Building Regulations have carried their own duty holder rules, and they point the same way. Where more than one contractor is involved, a principal designer and a principal contractor have to be appointed in writing. Where the client is a homeowner and no appointment is made, the regulations decide: the designer in control of the design becomes principal designer, and the contractor carrying out the work becomes principal contractor. The responsibility lands somewhere whether anyone has thought about it or not. We would rather it landed on us deliberately, in writing, and priced.

Chapter 04

Who we bring in, and whose contract they sit under

A technician draws it, an engineer calculates it, and specialist trades build it. All of them under our contract.

The architectural technician produces the measured survey, the existing and proposed drawings for the planning route, and the construction drawings the job is actually built from. On a straightforward extension that is what is genuinely needed, and it costs a fraction of what a full design service does.

The structural engineer sizes the beams, specifies the padstones, checks the masonry beneath the bearings, and designs the foundation where the ground or a tree demands something other than a standard trench. Their calculations are what Building Control checks. They are an independent professional with their own indemnity cover and their own name on the document.

The specialist trades are the groundworkers, bricklayers, roofers, electricians, plumbing and heating engineers, plasterers, glazing installers and tilers. You will meet them, know their names and talk to them on site. What you will not do is programme them, chase them, pay them or go back to them when something is wrong. That is ours.

If you already have drawings, or an engineer you have used before, we will work to them. We read them properly first and tell you plainly what we think, because we will be the ones carrying the consequence of building from them. That is not territorial. A design we have not checked is a risk we cannot price.

No obligation

Want this checked on your actual address?

Planning history, designation and deeds. We look at all three before anyone draws anything, and it costs you nothing.

Project Management & Main Contractor in the Colchester area
Fig. 05
Chapter 05

What we are not, and why we say it plainly

We are builders. Architecture and structural engineering are separate professions and we buy them in.

Architect is a title protected in law, and only someone on the statutory register may use it. A builder describing themselves as an architect is not exaggerating, they are committing an offence. So the distinction matters even before you get to competence.

Structural engineering is not protected in quite the same way, but the substance is identical. Calculations Building Control will accept come from someone with the qualifications, the software and, above all, professional indemnity insurance standing behind their signature. Public liability cover responds to injury and damage. It does not respond to a wrong number in a calculation. Indemnity is the policy that does, and it is why the calculation should come from someone who carries it.

So bringing in a technician and an engineer is not outsourcing the difficult parts. It is the correct arrangement, and every competent main contractor uses it. What we add is knowing which of them your job needs, at which point in the sequence, and precisely what to ask them for. Where this matters most is the builder who says you do not need an engineer for that. Occasionally true, for a very small opening with a standard lintel. Usually it means nobody wants to pay for the calculation, and Building Control will ask for it anyway.

Chapter 06

The sequence we run, and why the order matters

Seven stages. Each one sets the constraints for the next, which is why doing them out of order costs money.

The order is not administrative tidiness. Drawings produced before anyone has read the planning history get drawn to a depth a previous owner already used. Structural design commissioned before the planning route is settled has to be paid for twice when the scheme changes. Windows ordered before the openings exist arrive to a dimension that has moved. Ground broken before a build over agreement is in place stops when somebody notices the public sewer.

Stage What happens What it decides
1. Survey Ground, trees, drains, existing structure, access, planning history Whether the brief is buildable, and at what cost
2. Drawings Measured survey, existing and proposed What you are applying for
3. Permissions Certificate, prior approval or application. Party wall notices The shape and depth that gets built
4. Structural design Beams, padstones, foundation design The price of the dig and the shell
5. Building Control Full plans submission, decision, inspection schedule What has to be shown at each inspection
6. Build Groundworks through to second fix The programme
7. Handover Final inspection, completion certificate, snagging The paperwork you keep

Stages two, three and four overlap heavily in practice, and party wall notices run alongside everything because their periods are fixed and cannot be compressed except where the adjoining owner consents in writing, which is the only thing that shortens them. Running them in parallel is most of what shortens the front end of a job.

Fig. 02

The same wall, before and after

Drag to reveal. A real job in the Colchester area, photographed as it went. No staging and no borrowed images.

The completed extension, finished and clad The same elevation mid build, with the rear wall opened up During Finished
During — structure and claddingFinished — rear elevation
Project Management & Main Contractor in the Colchester area
Fig. 07
Chapter 07

What a proper quotation contains

A price on its own is not a quotation. What the number assumes is more useful than the number.

We survey before we price, and we price the house we have seen rather than the drawing. A quotation should tell you the scope in enough detail that you can see what is in it, the specification of the items that vary enormously, the assumptions written as assumptions, the exclusions, and the mechanism for when an assumption turns out to be wrong.

The assumption that matters most is the ground, because foundation depth cannot be known until something is dug. So the quotation states the depth allowed, states the rate for going deeper, and agrees in advance what happens if it does. That way the difference becomes arithmetic rather than a negotiation conducted next to an open hole in your garden.

Exclusions belong in the document rather than being discovered later. Ours are listed: VAT, kitchen units and appliances, floor coverings, decoration, professional fees for drawings and calculations, planning and Building Control fees, party wall surveyor fees if a neighbour dissents, service diversions, and anything genuinely unforeseeable once the ground is open. A quotation with no exclusions is not more generous than one with them. It is less finished.

Two prices are only comparable if they assume the same foundation depth, the same roof build up, the same glazing specification and the same level of electrical work. A large part of the gap between two extension quotes is specification rather than margin, and you cannot see that from the totals.

Chapter 08

Stage payments, and the deposit that goes wrong

Money follows completed work. That is the whole rule, and everything else is detail.

We work on stage payments against work actually done. A stage is a defined and visible point: foundations in and inspected, walls up to plate level, roof on and watertight, first fix complete. You can stand in the garden and see whether it has happened. A modest sum at the outset for materials ordered specifically for your job is normal. A large percentage of the contract value before anything is on site is not.

That single arrangement sits behind more bad outcomes than anything else in this trade, for a simple reason. Once the money is ahead of the work, the only leverage you have left is the money you have not yet paid, and there is not much of it. The test is easy to apply at any point in the job: add up what you have paid, look at what has been built, and if the first is meaningfully ahead of the second the structure is wrong regardless of who is doing the work.

Worth knowing as well: a contract you sign at your own kitchen table is an off premises contract, and the Consumer Contracts Regulations 2013 give you fourteen days to cancel it. If you want work to start inside that period you have to ask for it in writing, and where a trader never told you about the right at all, the cancellation period can extend by up to a year. A builder who handles that correctly is telling you something about how they handle everything else.

Why us

Five things you can check yourself.

Trust on a building job should be verifiable, not asserted. Every one of these can be confirmed without taking our word for it.

  1. 01
    Real company

    Essex Probuild Ltd, company 15979928, registered in West Bergholt. Checkable on Companies House in a minute.

  2. 02
    Real cover

    £2m public liability cover in place. Evidence available on request rather than a badge on a website.

  3. 03
    Real reviews

    4.6 out of 5 on Google from 10 reviews, shown as they were left. We do not curate them.

  4. 04
    Real photographs

    Every project image on this site is a job we built. No stock, and no fabricated before shots.

  5. 05
    Real accountability

    We notify Colchester City Council Building Control and manage the inspections through to your completion certificate.

Project Management & Main Contractor in the Colchester area
Fig. 09
Chapter 09

Variations, and finding something unexpected

We stop, we show you, we price it, and nothing proceeds until you have said yes in writing.

On a building job, finding something is a matter of when rather than if. Houses contain things nobody ever drew: a foundation shallower than the neighbours’, a drain running where no plan shows it, a beam bearing on almost nothing, rot behind a bathroom wall, a previous extension built without any of this ever happening.

Our process does not vary. We stop that element of the work. We photograph it and show you what is there. We explain the options, including doing nothing where doing nothing is genuinely an option. We price each one, and we tell you at the same time what it does to the programme. Then we wait for your written approval. We do not carry out extra chargeable work and present it at the end, because a variation you did not agree to is not a variation, it is a surprise. Not every discovery costs money either, and the ones that save money come back to you the same way.

The other kind of variation is the one you ask for. Changing your mind is allowed and on a long job it is normal. What it costs depends almost entirely on when. Moving a socket at first fix takes minutes. Moving it after plastering and decorating is a different conversation. Moving a window on a drawing is free. Moving it once the lintel is bedded is masonry, a new unit and a lead time.

Chapter 10

The programme, and what actually moves it

Some of it is ours to control. Some of it is fixed in law. Confusing the two is how impossible dates get promised.

What we control is the order of the trades, whether they turn up, whether materials were ordered early enough, whether the next stage is ready when the last one finishes, and whether a problem is dealt with in the week it appears rather than the month afterwards. That is the part a main contractor is actually being paid for.

What nobody controls starts with the statutory periods. A householder planning application has a determination period of eight weeks from validation. Larger home extension prior approval runs to forty two days. Party wall notice periods are one or two months depending on which section applies. Those are set in law and are shortened only by the adjoining owner consenting in writing, and not by us. Third party approvals have their own timescales, and a build over agreement may need a drain survey before it can even be applied for.

Then there is weather, which stops groundworks in a wet February and stops roofing in a gale, and lead times, because structural steel, rooflights and large glazed units are made to order. What we do about the parts we do not control is start them early and run them in parallel: party wall notices out while the planning route runs, steel ordered off the approved calculation rather than after the dig. We would rather give you a date that has allowed for the weather than one that assumes there will not be any.

Instrument 02

What might it cost?

A realistic range rather than a single number, with what it excludes shown as prominently as what it includes.

Type of work
Roughly how big
20 m²
Level of finish
Indicative range

£44k to £60k

Not included
  • VAT
  • Kitchen and appliances
  • Flooring
  • Decoration
  • Drawings and calculations
  • Planning and Building Control fees
  • Party wall surveyor
  • Service diversions

Indicative only. The biggest variable around Colchester is foundation depth, because most of the ground is shrinkable clay and mature trees are common. We price the job after seeing it.

Get a real price
Project Management & Main Contractor in the Colchester area
Fig. 11
Chapter 11

Who you speak to, and how often

One number, and the person who priced the job is the person running it.

Our team has 25+ years in the trade. He is the person who comes out to survey, the person who prices it and the person who runs it. You are not handed to somebody else once the contract is signed, which is a straightforward advantage of a business this size rather than a service promise.

Before anything starts we walk the programme with you stage by stage, so you know roughly what is happening in which week. After that there is a regular update at a frequency we agree at the beginning rather than one you have to ask for. During the disruptive phases, the dig, forming the opening, the roof going on, it is daily, because those are the weeks in which things actually change.

Anything carrying a cost or a decision goes in writing. Written does not mean formal: an email or a message with a photograph attached is fine. It means recorded, because verbal agreements on site are how two people leave the same conversation with different memories of it. And the days that affect your life get planned rather than announced: the day the back wall comes out, the day the water goes off, the day the drive is unavailable because the concrete is coming.

Chapter 12

What happens on your site

You are still living there. That is a constraint on how we work, not an inconvenience for you to absorb.

Protection comes first. Boarding on every route the work travels, dust screens at the boundary between the site and the house, and a proper sealed screen rather than a sheet taped to a door frame at the point where the wall comes out. Dust is the thing people underestimate most, and it is almost entirely preventable.

Working hours get agreed at the start. Noisy work is generally kept to reasonable daytime hours on weekdays and Saturday mornings, with nothing on Sundays or bank holidays, and a local authority has powers to impose limits where it needs to. Health and safety on site is ours too: under the Construction (Design and Management) Regulations 2015 the duties a commercial client would carry pass to the contractor on a domestic project, which is exactly where they belong.

Neighbours are told before the work starts rather than afterwards. Where the Party Wall Act applies they get formal notice. Where it does not, they still get a conversation, because they live with the noise and have no contract with anybody. On skips and access, a skip on your own drive needs nothing, while a skip or scaffolding on the public highway needs a licence from the highway authority with lights and markings. Where the only route to the back garden is through the house, that gets planned as a route, boarded, and given a set time of day for muck out. The site is left tidy at the end of every day and the house is left habitable.

Free survey

Get a real number, not a range.

We come out, look at the ground, the access and the structure, and price the job we have actually seen. The survey and the quotation are free.

Project Management & Main Contractor in the Colchester area
Fig. 13
Chapter 13

Snagging, handover and what you keep

The last two per cent takes longer than it looks, and it decides how the whole job is remembered.

Near the end we walk the work with you and write a list. Not a list we produce and hand over, a list you produce with us, in daylight, with time to look properly. Doors and catches, seals, paint edges, tile lines, a socket in the wrong place, anything at all that is not right.

Snagging is normal and a snagging list is not evidence of a job gone badly. Every building project has one. The meaningful difference is between a builder who invites the list and one who resents it, and between a list that gets booked in as a piece of work and one that gets chipped away at over four months. We book it.

At handover you get the paperwork, and you should keep all of it with your deeds. The completion certificate from Colchester City Council Building Control. The certification for the notifiable electrical work. The structural calculations and the approved drawings. The party wall award if there is one. Appliance and heating documentation where it applies. When you come to sell, a buyer’s solicitor asks for precisely these documents, and reconstructing them years afterwards is difficult and sometimes impossible. We also photograph what gets covered up as we go, so you have a record of where the drains and the cables run and what depth the foundation reached.

Chapter 14

Insurance, and the call to make before we start

Two policies matter, they cover different things, and neither one is a substitute for the other.

We carry £2m public liability cover. That is the policy that responds if we injure somebody or damage property in the course of the work. It is not an insurance of your building, and no contractor’s public liability policy is, whatever the figure on it.

Your buildings insurance is the other half, and this is the part people miss. Household policies commonly require you to notify the insurer before structural work begins, and some restrict cover for parts of the risk while it is underway: escape of water, theft from a building that is open, storm damage to an unfinished roof. If you have not told them and something happens, that argument arrives at the worst possible moment.

So ring them. Tell them what the work is, roughly how long it will take and roughly what it is worth. Many insurers simply note it. Some apply conditions or an additional premium. All of it is manageable in advance and none of it is manageable afterwards. It is also worth asking any builder for a copy of the certificate rather than accepting a statement that cover is in place. A certificate carries an insurer, a policy number, a limit and an expiry date. Ours is available on request, and you should ask, of us and of anybody else you are considering.

Survey stage of an extension buildDrawings stage of an extension buildPermissions stage of an extension buildStructure stage of an extension buildGroundworks stage of an extension buildStructure up stage of an extension buildFit out stage of an extension buildCertificate stage of an extension build Fig. 01
The programme

What actually happens, in order

Three of these eight stages happen before anybody digs anything. Get the order wrong and you pay to redo work.

  1. Survey

    We look at the ground, the trees, the access, the existing structure and where the drains actually run.

  2. Drawings

    A technician produces existing and proposed plans and elevations to a standard the council will accept.

  3. Permissions

    Permitted development, prior approval or a full application. We submit it and handle the correspondence.

  4. Structure

    The engineer calculates the beams, the padstones and the foundation depth for your ground.

  5. Groundworks

    Dig, concrete and drainage. The messiest phase and the one that decides whether the rest stands still.

  6. Structure up

    Walls, steel into the opening, roof on, windows and doors in. The day the back wall comes out is planned with you.

  7. Fit out

    First fix, plaster, second fix. From here it stops being a building site and starts being a room.

  8. Certificate

    Final inspection and your Building Control completion certificate. Keep it with the deeds.

Project Management & Main Contractor in the Colchester area
Fig. 15
Chapter 15

How to compare us against another quote

These are not sales questions. Ask them of us as well, and compare the answers rather than the totals.

Every one of these has a good answer and a vague answer, and the difference between the two is usually the difference between the prices.

  • What foundation depth have you allowed, and what is the rate if it goes deeper? A number and a rate. Vagueness here means the figure is a deposit rather than a price.
  • Who produces the drawings and who produces the structural calculations, and is that inside your price or mine to arrange?
  • Are the trades your sub-contractors, or is it my job to appoint them?
  • What is the payment schedule, and how much is due before anything is on site?
  • What is excluded? A short exclusions list is a warning rather than a benefit.
  • How are variations priced and approved, and what happens if I am not there that day?
  • Who is my point of contact once work starts, and is it the person quoting?
  • May I see the public liability certificate?
  • Who notifies Building Control, who books the inspections, and who obtains the completion certificate?
  • What is the defects process after handover, and where is it written in the contract?

If two builders answer those ten questions and one price is twenty thousand pounds lower, you will usually be able to point at exactly which answers the difference lives in. That is the entire purpose of asking.

Chapter 16

Questions we get asked

Can I project manage it myself and use you only for the building work?

Yes, and some people do it well. Be honest with yourself about what you are taking on: the sequencing, the chasing, the arbitration between trades, and the risk that sits in the gaps between separate appointments. With building experience, or with time and patience in quantity, it can save money. With a full time job and no experience, the saving is often smaller than the delays cost.

Is a main contractor more expensive than arranging it all yourself?

The co-ordination is priced rather than free, so on paper it looks that way. In practice the comparison rarely runs how people expect, because the separate route carries costs that appear in nobody’s quotation: the weeks lost to a disagreement, the trade you have to re-book, the unit ordered to a dimension that changed. We will not put a figure on that, because we cannot evidence one. What we will say is that our price includes the co-ordination, and you should check whether the price you are comparing it against does.

What do we actually sign?

A written contract carrying the scope, the specification, the price, the stage payments, the programme, the variation procedure and the defects provisions. There are standard forms written for domestic building work of exactly this kind. Which document matters less than the fact that everything you were told verbally appears somewhere inside it.

What happens if we disagree about something?

The written record comes out first, and most disagreements dissolve at that point because they were misunderstandings rather than disputes. Where one does not, we put our position and what we propose to do about it in writing, and there is a complaints procedure on this site setting out the steps and the timescales. Nobody enjoys that conversation. The ones that go badly are the ones nobody wrote anything down about.

Project Management & Main Contractor in the Colchester area
Fig. 17
Chapter 17

How we work

One contract, one contact, and the paperwork is our problem rather than yours.

Probuild Extensions Colchester is the extensions arm of Essex Probuild Ltd, company 15979928, based in West Bergholt about three miles north west of the city centre. We cover Colchester and roughly thirty miles around it.

Our team comes out and surveys the property, and the first visit is a survey rather than a sales call. Most people who call us already have drawings and permission and want a builder to price the work and build it. That is the ordinary job here, and we are glad to work to somebody else’s plans. Where the drawings do not exist yet, we bring in the technician who draws it and the structural engineer who calculates it, we manage the planning route, we notify Colchester City Council Building Control and deal with the inspections, and we run the trades as main contractor through to the completion certificate. We carry £2m public liability cover and everything is built to current Building Regulations.

We are rated 4.6 out of 5 on Google from 10 reviews, shown on this site exactly as they were left. The survey and the quotation cost nothing, and there is no pressure afterwards.

Last reviewed August 2026. Planning rules and Building Regulations change, and your property may differ, so treat this as a guide rather than advice on your specific job.

Get a quote

Tell us what you are planning.

We will come and look at the property, talk through what is realistic, and put a proper number to it. No obligation, and no pressure afterwards.

  • We bring the drawings, the structural engineer and the Building Control notification. You ring one number.
  • Our team has 25+ years in the trade, and he is the one who turns up.
  • £2m public liability cover in place. Work built to current Building Regulations.
  • Straight answers on what a job depends on, before we talk about what it costs.

Request a quote

Takes about a minute. We reply to everything.

07487 706530