Squaring off a hipped roof to make a loft usable, which is exactly what the 1930s semis around Lexden need.

A hipped roof takes the width out of your loft at exactly the point where a bedroom needs it. Squaring the hip off into a vertical gable gives that width back without touching the ridge height, and on the interwar semis across Lexden, Prettygate and Shrub End it is usually the difference between a loft that works and one that does not.

Hip to Gable Loft Conversions in the Colchester area
Fig. 01
Chapter 01

What a hipped roof is, and why it wastes the loft

The hip slopes the roof inwards from three or four sides, so the loft tapers away to nothing at the end.

A gabled roof has two slopes and two vertical triangular walls at the ends. A hipped roof slopes on the ends as well, so instead of a flat brick triangle you get a third and fourth plane of tiles running back from the eaves up to the ridge. It is the standard roof on speculative housing built between about 1920 and 1939, and it is why so much of Colchester’s suburban stock looks the way it does.

Structurally the hip is elegant. Diagonal hip rafters run from each corner of the wall plate up to the end of the ridge, jack rafters cut into them, and the whole corner triangulates itself. It is stiff, it sheds water well, and it needs no gable wall.

Inside, it is a problem. Head height in a roof is a function of how far you are from the eaves, and the hip pulls the roof surface inwards on the end elevation as well as the front and back. The zone with two metres or more above the floor is not a rectangle, it is a lozenge, and the hip shortens that lozenge at one end by roughly the same distance as the height of the roof above the eaves. On a house with a seven metre span and a forty five degree pitch, the hip is eating about three and a half metres off the length of the usable room.

That is not a corner you can lose gracefully. It is the end of the room, and it takes the bed wall with it.

Chapter 02

What squaring it off actually involves

Take the hip off, extend the ridge, build a masonry wall up to meet it, and re-roof the end.

The sequence is the same on almost every house, and knowing it helps you read a quotation.

Scaffold goes up all round with a proper working lift at eaves level and a temporary roof over the opened section. The tiles and battens come off the hip end and are stacked for reuse where they are sound, because matching a 1930s clay plain tile from stock is not always possible and the salvaged tiles are worth keeping.

The hip rafters, jack rafters and the end section of the wall plate come out. The ridge is then extended horizontally out to the new gable position, carried on the new gable wall at one end and picked up by the retained roof structure at the other, with new purlins to match the existing runs.

The gable itself is built up off the flank wall below it. On a cavity wall that means both leaves carried up, cavity maintained, wall ties at the correct centres, and a cavity tray and weep holes where the new work meets anything below. New common rafters land on a new wall plate strapped to the gable, a gable ladder is formed to carry the verge, and lateral restraint straps tie the new wall back into the rafters and into the new floor.

Then it is tiled and weathered, the verge is detailed, and the outside is made to look as though it has always been that way. That last part is more of the job than people expect.

Hip to Gable Loft Conversions in the Colchester area
Fig. 03
Chapter 03

How to tell what roof you have

Hipped, half hipped or gabled. Stand across the road and look at the end of the house.

A gabled roof shows you a vertical triangle of brickwork or render at the end, running right up to the ridge. Nothing to square off, because it is already square. Your loft conversion is a dormer or rooflight question instead.

A hipped roof shows you tiles all the way, sloping back from the eaves to a ridge that stops short of the end wall. This is the one the page is about.

A half hipped roof, sometimes called a jerkin head or a clipped gable, starts as a gable and then cuts the top off at an angle, so you get a triangle of brick low down and a small sloping tiled panel above it. These appear on Arts and Crafts influenced housing and on some 1930s estates. They convert the same way, and there is usually less to build because part of the wall is already there.

Two further things to check while you are outside. Look at whether the hip is on the flank of the house or over a projecting front bay, because a hipped bay roof on an otherwise gabled house is a different and much smaller job. And look at your neighbour. On a semi the pair was almost always built as a mirrored set with a hip at each outer end, which matters for planning in a way we come to further down.

Instrument 01

Will you need planning permission?

Four questions, an honest answer, and nothing sent anywhere. This runs entirely in your browser.

What are you extending?

Permitted development rights for extensions apply to houses. Flats and maisonettes are a different route entirely.

Is the property listed?

Listed building consent is a separate decision from planning permission, and work without it is a criminal offence rather than a planning irregularity.

Has the house been extended before?

Depth is measured from the ORIGINAL rear wall, so a previous owner's extension has already used part of your allowance. This catches almost everybody.

Is it in a conservation area?

Colchester has a number of them, including the historic core, the Dutch Quarter, part of Lexden and several village centres. The boundaries rarely follow the roads you would expect.

Indication only

Answer the four questions for an indication

Whatever the answer, Building Regulations approval is always needed. We check the planning history, the designation and the deeds on your address before anyone draws anything, because it decides the design rather than the other way round.

This is an indication based on four questions, not advice on your property. Planning rules change and the position depends on your specific address, its planning history and its designation.

Chapter 04

Why this is the defining conversion for the interwar semi

Everything else about that house type is already right. The hip is the only thing in the way.

A typical 1930s Colchester semi has a traditional cut roof with rafters, purlins and struts, a pitch somewhere between forty and forty five degrees, and a ridge height that gives around 2.4 metres above the ceiling joists. The timber is usually sound, the loft is usually dry, and the head height is usually there.

It also has a landing with enough length to take a staircase over the existing one, a flank wall that can generally carry more load, and a rear elevation that is not the principal elevation, which is the elevation that matters most for permitted development.

What it does not have is width at height. The hip removes it, and no amount of clever internal planning gets it back. You can convert a hipped loft without touching the hip, and people do, but what you end up with is a room that is generous at one end and a crawl space at the other, with the wardrobe wall missing and nowhere sensible for the stairs to arrive.

Square the hip off and the room becomes rectangular. Add a dormer to the rear slope and it becomes a double bedroom with an en suite and a proper landing at the top of the stairs. That combination is the reason this conversion is so common on that house type, and it is why the two are usually priced together rather than separately.

Hip to Gable Loft Conversions in the Colchester area
Fig. 05
Chapter 05

The permitted development volume allowance

Roof extensions are measured in cubic metres, cumulatively, and a hip to gable spends a real share of the allowance.

Additions to a roof have their own permitted development class, and the allowance is a volume of additional roof space: broadly 40 cubic metres for a terraced house and 50 cubic metres for a semi detached or detached house. It is cumulative and it counts everything ever added to the roof, so a house that already has a small dormer has already spent part of it.

The volume a hip to gable adds is the wedge of space between the new vertical gable and the old sloping hip. You can work it out from the geometry. On a house with a seven metre span and a forty five degree pitch, the hip sets back about 3.5 metres from the end wall, the gable triangle is around 12 square metres, and the wedge comes out in the region of 14 cubic metres. On a shallower forty degree pitch the same house is nearer 10.

A full width rear box dormer on the same house is commonly in the region of 20 to 30 cubic metres once you subtract the roof slope it replaces. Put the two together and you are frequently at or over the 50 cubic metre allowance for a semi, and comfortably over 40 on a terrace.

This is the single most common reason a hip to gable plus dormer scheme needs a planning application rather than a certificate. It is arithmetic, not opinion, and it is worth doing properly on the actual measurements of your house before anyone tells you which route you are on.

Measure the volume from the drawings rather than assuming. Two houses that look identical from the road can sit either side of the allowance because of a metre of span or five degrees of pitch. The calculation takes an hour and it decides whether you are applying for a certificate or an application, which changes both the programme and the risk.

No obligation

Want this checked on your actual address?

Planning history, designation and deeds. We look at all three before anyone draws anything, and it costs you nothing.

Chapter 06

The other conditions attached to the allowance

Volume is the headline. The conditions are where schemes actually come unstuck.

Nothing may be higher than the highest part of the existing roof. A hip to gable does not raise the ridge, so this one is normally satisfied, but it does mean that if the head height is not there already, squaring off the hip will not create it. The gable gives you width and floor area, never height.

No part of the enlargement may extend beyond the plane of the existing roof slope on the principal elevation where that elevation fronts a highway. On a standard semi the hip is on the side, so this is not engaged. On a corner plot, or a house set at an angle to the road, it needs checking rather than assuming.

Materials must be similar in appearance to the existing house. On a gable that is a serious specification point rather than a formality, because you are creating a new elevation of brickwork or render several metres square, in full view from the street.

Any window in a side elevation at upper floor level has to be obscure glazed and non opening below 1.7 metres from the floor. A new gable is a side elevation, so a window in it is caught by this. Plenty of people plan a gable window for the view and then discover it has to be obscured.

There is also a condition about the enlargement being set back around 200mm from the eaves, written as “so far as practicable”. It is the condition most often argued about on a hip to gable, because the new wall is built up in the line of the wall below it. Resolve that on paper before the scaffold goes up.

Hip to Gable Loft Conversions in the Colchester area
Fig. 07
Chapter 07

What removes permitted development, and what a conservation area does

A roof extension in a conservation area is not permitted development at all. That is the single biggest constraint on this job.

Permitted development for roof additions does not exist for flats and maisonettes. On a listed building it is not removed either, but listed building consent applies as a separate and additional requirement, and on a historic roof that is generally the harder of the two to satisfy.

More importantly for this conversion, the class is switched off entirely on what the legislation calls article 2(3) land. That includes conservation areas and National Landscapes, the designation formerly known as areas of outstanding natural beauty. It is not a restriction or a tightening. Any addition to the roof in those areas is a full planning application.

That matters here more than for almost any other conversion, because a hip to gable is visible. A rear dormer can hide behind a roof and be invisible from the street. A gable changes the outline of the building against the sky from the pavement opposite, permanently. Officers know this and so does everybody who lives on the road.

Locally that puts parts of Lexden inside a conservation area, along with the historic core of the city and village centres including Dedham and Wivenhoe. Coggeshall is designated too, but it is Braintree District that decides there. Dedham Vale is a National Landscape, which catches property well outside the village itself. An Article 4 direction can remove permitted development rights over a defined area for defined types of work, and where one is in place it does exactly what it says.

None of this makes the conversion impossible in those areas. It makes it an application, on merits, with design that has to answer for itself.

Chapter 08

Estate conditions on newer housing

Permitted development rights are frequently removed by condition on estates built from the 1980s onwards.

When an estate is granted permission, the planning authority can attach a condition removing permitted development rights from the houses within it, usually to keep control of the appearance of the scheme as a whole. It is common on developments in Stanway, Myland, Highwoods and the newer edges of Prettygate, and it is the thing almost nobody checks.

It costs nothing to check. The council’s online planning search holds the original estate permission and the conditions attached to it, and ten minutes reading the decision notice tells you whether the rights exist. We do this before quoting rather than after.

Newer housing brings a second complication anyway, which is that the roofs are usually trussed rather than cut, and often at a shallower pitch. Those two things together mean the honest answer on a lot of 1980s and 1990s hipped houses is that the conversion is possible but neither cheap nor simple, and that it wants looking at properly before anybody gets attached to the idea.

A restrictive covenant on the title is different again. It is private law rather than planning, it does not show up on the council’s system, and your conveyancing file is where it will be. Covenants on estate housing sometimes restrict alterations to the exterior. Worth a look at the deeds while you are checking everything else.

Fig. 02

The same wall, before and after

Drag to reveal. A real job in the Colchester area, photographed as it went. No staging and no borrowed images.

The completed extension, finished and clad The same elevation mid build, with the rear wall opened up During Finished
During — structure and claddingFinished — rear elevation
Hip to Gable Loft Conversions in the Colchester area
Fig. 09
Chapter 09

Semi-detached symmetry, and why officers weigh it

A pair of hipped semis was designed as one building. Squaring off one half changes the whole thing.

This is the design question that comes up more than any other on this conversion, and it is a legitimate planning consideration rather than a neighbour’s opinion.

A 1930s semi-detached pair is symmetrical about the party wall: two bays, two porches, two hips, one composition. Build a gable on one end and the building is no longer balanced. From directly in front it can read as a slightly lopsided single house, and from an angle it reads as two houses that no longer match.

Officers do weigh this, and they weigh it differently depending on the street. On a road where several pairs have already been squared off, the harm is limited because the character of the street already includes gables. On an intact terrace of pairs where none has been altered, the same application is a harder argument. Neither outcome is predictable from a distance and we would not pretend otherwise.

Where the design can respond, it usually does so in one of three ways. Matching materials honestly, so the gable reads as part of the original building rather than an addition: the right brick, the right bond, a mortar mix matched to what has weathered on the house rather than to whatever the merchant has in stock. Setting the gable back slightly from the front elevation, or keeping a small return of hip at the front corner, which softens the change from the street while still gaining the internal space. And occasionally both halves converting, either together or with one designed so the other can follow, which restores the symmetry completely.

The last of those is not always possible and it is never something you can rely on your neighbour to do. It is worth a conversation though, because a pair converted as a pair is the strongest version of this scheme by a distance.

Chapter 10

Lawful Development Certificates

Where the work is permitted development, get it in writing. A loft bedroom is what a buyer’s solicitor asks about.

A Lawful Development Certificate is a formal determination by the council that what you have built, or propose to build, did not need planning permission. It is not permission and it is not a favour. It is a factual decision on the drawings you submit.

It matters most on a conversion, because the thing you have created is a bedroom, and a bedroom on a sale is scrutinised. A prospective buyer’s solicitor asks two questions about a converted loft: was planning dealt with, and was Building Control. The certificate answers the first and the Building Control completion certificate answers the second. Without them, the answer is a retrospective indemnity policy and an awkward month in a chain.

On a hip to gable there is a further reason. Because the volume calculation is fine, and because the conservation area position and the estate conditions both bite hard, a certificate is the difference between a considered judgement and somebody’s confident guess. If the council determines the scheme is lawful, that is the end of the argument.

Where a full application is needed instead, that is a different route with a statutory eight week period from validation, and a different set of questions about design. We will tell you which one we think you are on and why, and we will not tell you what the answer will be, because nobody honest can.

Why us

Five things you can check yourself.

Trust on a building job should be verifiable, not asserted. Every one of these can be confirmed without taking our word for it.

  1. 01
    Real company

    Essex Probuild Ltd, company 15979928, registered in West Bergholt. Checkable on Companies House in a minute.

  2. 02
    Real cover

    £2m public liability cover in place. Evidence available on request rather than a badge on a website.

  3. 03
    Real reviews

    4.6 out of 5 on Google from 10 reviews, shown as they were left. We do not curate them.

  4. 04
    Real photographs

    Every project image on this site is a job we built. No stock, and no fabricated before shots.

  5. 05
    Real accountability

    We notify Colchester City Council Building Control and manage the inspections through to your completion certificate.

Hip to Gable Loft Conversions in the Colchester area
Fig. 11
Chapter 11

Structure: what carries the new gable

The hip was spreading its load around a corner. A gable puts it down one wall.

This is the part of a hip to gable that gets least attention in quotations and causes the most trouble on site.

A hipped corner distributes roof load into two walls at once, through the diagonal hip rafter and the jack rafters either side. Remove it and build a gable, and you have added several tonnes of masonry in a triangle, sitting on one wall, plus the roof loads that wall now carries directly. The flank wall of a 1930s semi was built to hold up a roof edge, not a gable.

Usually it can take it, because masonry in reasonable condition has a lot of capacity in compression. What it cannot always take is load over an opening. Look along the flank wall below the hip and find every opening in it: a side door, a landing window, a kitchen window, the head of a bay that returns round the corner, or the opening into an attached garage. Each of those has a lintel that was sized for what was above it in 1935 and not for a gable.

Where an existing lintel is inadequate it is replaced or supplemented, which means propping and needling the wall above while the new one goes in. Where a beam is introduced, its ends land on padstones, precast or in situ concrete blocks that spread a concentrated point load into masonry that would otherwise crush locally under it.

An attached garage is the classic case. A single skin garage wall will not carry a gable, and the answer is usually a beam over the garage opening with new piers or padstones at each end, which is a real cost and one that should appear in the quotation rather than in week four.

Chapter 12

Foundations and when to dig a trial hole

You are adding load to a footing nobody has looked at since it was poured.

A 1930s strip footing is typically shallow by modern standards, often 450 to 600mm deep, sometimes a stepped brick footing rather than concrete, and it was designed for the house that sits on it. A hip to gable adds load to the wall above it, so the question of whether the footing can take that load is a real one rather than a formality.

In many cases the added load is modest relative to what is already there and no work is needed. The engineer will say so on the basis of what is found, not on the basis of hope.

A trial hole is how you find out. It is a hand dug hole against the outside of the flank wall, taken down past the bottom of the footing, exposing its width, its depth and the soil beneath it. It takes half a day and it settles the argument. Where the footing is shallow, narrow or sitting on made ground, the options are underpinning a length of it, casting a new pad beneath a beam bearing point, or redesigning the gable to reduce weight.

Ground around Colchester is varied. The higher ground to the west and north sits on clay, and clay is shrinkable, which makes nearby trees and their species a genuine input. Closer to the Colne valley you find sands and gravels, which behave differently again. This is why the answer is a trial hole rather than a rule of thumb.

Reducing the weight is an option worth knowing about. A gable can be built as a timber framed panel above first floor ceiling level, clad in tile hanging or render board, rather than in masonry. It is dramatically lighter, it goes up faster, and whether it looks right depends entirely on the street. On a road of plain brick gables it will not. On a road with tile hung gables already, it will.

Hip to Gable Loft Conversions in the Colchester area
Fig. 13
Chapter 13

The roof structure change in detail

Hip rafters out, ridge extended, purlins run through, and the whole end re-braced.

The hip rafters are doing structural work and they cannot simply be cut out and the space enjoyed. Removing them removes the triangulation at that corner, so the replacement structure has to be in place, or temporarily propped, before they go.

The ridge is extended out to the new gable. Where the existing ridge board is a slender 1930s section, the extension is usually a new timber sized by calculation, spliced or supported so the two work together, and on wider spans it becomes a ridge beam carried on the gable at one end and a post or wall below at the other.

The purlins matter more than the ridge. On a cut roof the purlins carry the rafters at mid span, and they are usually supported by struts landing on a load bearing internal wall or on binders. Extending the roof to a new gable means extending or replacing those purlins so the new rafters are supported at mid span too, and the new purlin ends bear into the gable on padstones. Getting this wrong is what produces a roof that sags at the new end after a few winters.

New common rafters are then set out at matching centres, birdsmouthed onto a new wall plate that is strapped down to the gable masonry, with the verge formed by a gable ladder oversailing the wall.

Lateral restraint is not optional. A newly built gable is a tall panel of masonry with wind on both faces and nothing holding the top of it. Galvanised restraint straps tie it back into the rafters and into the new floor structure at defined centres. Missing straps are one of the more common defects we find on gables built by somebody else.

Instrument 02

What might it cost?

A realistic range rather than a single number, with what it excludes shown as prominently as what it includes.

Type of work
Roughly how big
20 m²
Level of finish
Indicative range

£44k to £60k

Not included
  • VAT
  • Kitchen and appliances
  • Flooring
  • Decoration
  • Drawings and calculations
  • Planning and Building Control fees
  • Party wall surveyor
  • Service diversions

Indicative only. The biggest variable around Colchester is foundation depth, because most of the ground is shrinkable clay and mature trees are common. We price the job after seeing it.

Get a real price
Chapter 14

Trussed rafter roofs, and why they change the job

If the loft is full of diagonal timbers, the conversion is a different and larger project.

Housing from roughly the mid 1960s onwards is generally built with trussed rafters: prefabricated triangulated frames, delivered whole, with diagonal webs across the middle of the space. They are efficient and they are cheap, and every part of them is carrying something.

You cannot cut the webs out to make a room. What you can do is install new structure that takes over everything the trusses were doing, and only then remove what is in the way. In practice that means new steel or engineered timber beams at ridge and mid span level, new floor structure independent of the ceiling ties, and a sequence of work where the new is in and loaded before the old comes out.

On a hip to gable this compounds, because hipped trussed roofs use a set of shortened girder trusses and jack rafters at the hip end, and the girder truss is carrying the ones behind it. Squaring off means dealing with that girder truss as well as the hip itself.

It is entirely doable. It is not the cheap conversion people assume a loft to be, and it is the version most likely to be quoted by somebody who priced it from the pavement without going into the loft. Shallow pitches on the same generation of housing frequently mean the head height is not there either, which turns a hip to gable into a hip to gable plus a substantial dormer before you have gained a usable room.

If you have a trussed roof, the useful thing we can do is tell you early whether the numbers work, so you are not paying for drawings of something that was never going to be sensible.

Hip to Gable Loft Conversions in the Colchester area
Fig. 15
Chapter 15

The new floor

Ceiling joists hold a ceiling up. A floor is a different order of load entirely.

The timbers currently spanning your loft were sized to carry plasterboard and a few boxes. They are not a floor and boarding over them does not make them one.

A conversion introduces new floor joists, deeper than the existing ceiling joists, usually carried at each end on steel beams. Those steels typically run across the house and bear into the party wall on one side and the flank wall on the other, which on this conversion is the wall you have just built a gable on top of. The two things interact, and they should be designed together rather than by two people on different days. A chimney breast standing in the loft is part of the same design.

Steel bearings are concentrated point loads landing on walls that were carrying distributed ones, so each end sits on a padstone. The pocket is cut, the padstone bedded, the beam craned or manhandled in and packed, and the masonry made good above it. On a semi, cutting that pocket into the party wall is the trigger for a formal notice, which is the next section.

The new joists sit above the existing ceiling joists rather than replacing them, so the old ceiling below stays intact and undisturbed. That is why head height gets eaten from both directions at once, roughly 150mm at the floor and around 300mm at the ceiling once insulation, structure and plasterboard are in.

It is also why the 2.4 metre figure matters so much. Take 450mm off 2.4 and you have just under 2 metres of finished height at the ridge, which is the working minimum for a room that feels like a room.

Chapter 16

The Party Wall etc. Act 1996

Three sections can apply on a hip to gable, and they carry different notice periods.

This is a legal process, not a dispute, and it applies to the great majority of hip to gable conversions on semi-detached and terraced houses. It is served by you as the building owner, and it is our job to tell you when and which.

Section 2 covers work to a party structure. Cutting a pocket into the shared party wall to seat a floor steel is section 2 work, as is raising or altering that wall where the roof change requires it. A party structure notice requires two months before work starts.

Section 1 covers building a new wall at the line of junction between two properties. It comes into play on a hip to gable where the flank wall you are building on sits on or very close to the boundary with the neighbour on the open side, which on a semi it very often does. A line of junction notice requires one month.

Section 6 covers excavation within three metres of a neighbouring structure to a lower depth than its foundations, and within six metres in certain circumstances. On this job it is triggered by trial holes, new pad foundations under a beam bearing, or any underpinning. Section 6 notices also require one month.

Where a neighbour consents in writing, that is the end of it. Where they dissent, or simply do not respond within fourteen days, surveyors are appointed and an award is drawn up. That award records the condition of their property beforehand in a schedule of condition and sets out how the work proceeds. You pay for it, and on a semi it is a budget line rather than a remote possibility.

The advice that costs nothing and works: tell your neighbour yourself, with the drawings, before a formal notice arrives. The schedule of condition protects both of you, and it is what prevents an argument in eighteen months about a crack that was already there.

Free survey

Get a real number, not a range.

We come out, look at the ground, the access and the structure, and price the job we have actually seen. The survey and the quotation are free.

Hip to Gable Loft Conversions in the Colchester area
Fig. 17
Chapter 17

What the gable actually gains you

Width and floor area at full height. Not height, and not more roof.

It is worth being precise about this, because the gable is often oversold and occasionally undersold.

What you gain is the wedge of space the hip was taking: on a typical semi, roughly the last 2.5 to 3.5 metres of the room at the hip end, restored to the full width of the roof. In floor terms, on a house where the usable zone was around 3 metres by 3.5, the gable can take it to something nearer 3 by 6. That is the difference between a study and a bedroom.

Just as importantly, it gives you a full height wall at one end of the room. Every piece of furniture that needs a vertical surface behind it, which is most furniture, now has somewhere to go. It also gives the staircase somewhere sensible to arrive, because you can land at the gable end with head height above you.

What you do not gain is any additional height at the ridge. If your loft measures 2.2 metres from ceiling joist to ridge, it will still measure 2.2 metres afterwards, and squaring the hip off will not fix a head height problem. That needs a dormer, a raised ridge or a lowered ceiling below, all of which are different projects with different costs.

You also do not gain much on the plan area under two metres. The eaves are where the eaves were, and the low margins at the front and rear stay low. Those become storage, which is genuinely useful, but they are not floor area you stand up in.

Chapter 18

Why it is usually paired with a rear dormer

The gable gives length, the dormer gives width at height. Together they give you a room.

On a hipped semi, the gable alone typically produces a long room with head height along a strip down the middle and sloping ceilings either side. It works, and where budget is the constraint it is a legitimate scheme with rooflights only.

Add a box dormer to the rear slope and the character changes. The dormer creates full ceiling height across whatever width it covers, which is where the bed, the wardrobes and usually the en suite end up. The gable then extends that full height zone the length of the house rather than leaving it stranded in the middle.

The two also cooperate structurally, because the dormer’s floor and its side cheeks tie into the same new floor structure and the same steels. Doing them together is meaningfully cheaper than doing one and returning for the other, mostly because you pay once for scaffold, once for the roof being open, and once for the disruption.

The catch is the one already covered: the combined volume is what pushes the scheme past the permitted development allowance on a lot of houses. That is not a reason to avoid the dormer. It is a reason to know before you start whether you are applying, because it changes the programme by two to three months and it changes what the design has to answer for.

Where the volume is tight, the usual lever is dormer width. A dormer set in from both sides, with a set back from the eaves and the ridge, uses noticeably less volume than a full width box and frequently looks better from the garden. The internal loss is smaller than people fear.

Hip to Gable Loft Conversions in the Colchester area
Fig. 19
Chapter 19

Part B, fire, and the protected stairwell

Adding a third storey changes the escape route for the entire house.

This is the item people are least prepared for and it is usually the biggest cost after the structure.

A two storey house escapes through its windows. A three storey house cannot, because you cannot safely drop from a second floor. So the staircase becomes the escape route, and it has to be protected from the top floor all the way down to the final exit door.

In practice that means fire doors on every habitable room opening onto the stairwell, on every floor, not just the new one, fitted with intumescent strips and cold smoke seals and hung so they actually close. It means the walls and ceilings enclosing that stairwell achieving 30 minutes fire resistance, which on a 1930s house with lath and plaster usually means overboarding. It means interlinked mains powered smoke alarms on every level. And it means the new floor achieving 30 minutes fire resistance from below.

Where a protected stairwell is genuinely impossible, most often where a previous owner opened the ground floor up and the stairs now come straight into the living room, there are alternative approaches. A sprinkler or misting system, or an escape window arrangement to a place of safety, both subject to Building Control agreeing them. They are legitimate, they cost money, and they need agreeing before work starts rather than at first inspection.

An escape window is required in every habitable room in the loft: at least 0.33 square metres of clear opening, at least 450mm in each direction, with the bottom of the opening between 800mm and 1100mm above the finished floor. On a hip to gable that constrains where the dormer window sits and whether a gable window can serve the purpose, so it is a design input rather than a later decision.

Survey stage of an extension buildDrawings stage of an extension buildPermissions stage of an extension buildStructure stage of an extension buildGroundworks stage of an extension buildStructure up stage of an extension buildFit out stage of an extension buildCertificate stage of an extension build Fig. 01
The programme

What actually happens, in order

Three of these eight stages happen before anybody digs anything. Get the order wrong and you pay to redo work.

  1. Survey

    We look at the ground, the trees, the access, the existing structure and where the drains actually run.

  2. Drawings

    A technician produces existing and proposed plans and elevations to a standard the council will accept.

  3. Permissions

    Permitted development, prior approval or a full application. We submit it and handle the correspondence.

  4. Structure

    The engineer calculates the beams, the padstones and the foundation depth for your ground.

  5. Groundworks

    Dig, concrete and drainage. The messiest phase and the one that decides whether the rest stands still.

  6. Structure up

    Walls, steel into the opening, roof on, windows and doors in. The day the back wall comes out is planned with you.

  7. Fit out

    First fix, plaster, second fix. From here it stops being a building site and starts being a room.

  8. Certificate

    Final inspection and your Building Control completion certificate. Keep it with the deeds.

Chapter 20

The staircase, and where it lands on a 1930s semi

Part K decides the geometry. The existing landing decides the position.

Part K sets a maximum pitch of 42 degrees, a minimum going and maximum rise, handrail requirements, and 2 metres of headroom measured vertically above the pitch line. That headroom requirement is what usually decides where the stairs can go, because they have to rise through the existing roof structure and there has to be height above them at the top.

On a standard 1930s semi the answer is nearly always over the existing staircase, running in the same direction, so the circulation stacks and the new flight arrives on the landing above the old one. The landings on that house type generally have the length for it, which is one of the reasons the house type converts so well.

The hip to gable helps here in a way that is easy to miss. Because the gable end now has full height, the top of the stairs can arrive against or near it with 2 metres above, instead of arriving into a sloping ceiling. On an unaltered hipped roof the only place with height is the middle, which is also the only place the room wants to be.

The cost of the stairs is space on the first floor landing. A new flight and the trimmed opening take floor area from somewhere, and on a small semi that sometimes clips the corner of the smallest bedroom or the airing cupboard. It is better to see that on a drawing early than to discover it later.

Alternating tread space saver stairs are permitted in defined circumstances for a loft conversion. They are a genuine last resort rather than a way to save space, they are unpleasant with laundry, and Building Control will want to be satisfied about what the room they serve is used for.

Hip to Gable Loft Conversions in the Colchester area
Fig. 21
Chapter 21

Insulation, condensation and summer heat

The new gable is a whole new elevation of external wall, and the roof is where the house loses most heat.

Part L applies to the new thermal elements. On a hip to gable that includes the roof, and it also includes the gable wall itself, which is a new external wall several metres square that has to perform.

The roof is either a cold roof, with insulation between and under the rafters and a ventilated void above it, or a warm roof, with insulation above the rafters and the structure kept on the warm side. Cold roof is the usual approach on a conversion because it keeps the external roof line unchanged, and it depends entirely on maintaining a clear ventilation path from eaves to ridge, typically 50mm, with ventilation at both. Fill that path with insulation, which is easy to do by accident, and you get condensation in the roof void and rot in the timbers you just paid to strengthen.

The junction between the new gable and the roof insulation is a specific weak point. Insulation has to be continuous around that corner, or you get a cold bridge running the full height of the wall, which shows up as a damp stripe and eventually mould in the corner of the new bedroom.

Summer is the bigger practical problem. A loft has more roof exposed to the sun than any other room, and a new gable facing south or west absorbs heat all afternoon. Overheating is genuinely relevant here rather than a box to tick. Approved Document O sets requirements for new dwellings rather than conversions, so it does not formally apply, but a converted loft sits directly under the roof and the physics is the same. Solar control glazing in rooflights and dormer windows, insulation depth above the minimum rather than at it, and openable windows positioned so warm air can leave at the high point all make a measurable difference.

Heating is worth checking too. The loft is the furthest point from the boiler, the flow and return runs are long, and adding a floor increases the load. A separate zone with its own thermostat is a small cost at first fix and a large difference afterwards.

Chapter 22

Water tanks, cylinders and the plumbing consequences

Whatever is sitting on the loft joists has to go somewhere, and moving it changes the whole house.

Most 1930s semis that have not been modernised have a cold water storage tank and a smaller feed and expansion tank sitting on the ceiling joists, usually right in the middle of where the new bedroom goes.

Where the house already has a combi boiler, the tanks are redundant and simply come out, which is the easy outcome. Where the system is vented, with a hot water cylinder in the airing cupboard, the tanks are doing a job and there are three options: relocate them onto a supported platform in whatever roof space remains, convert to an unvented cylinder, or convert to a combi. Each has a different cost and each changes the water pressure everywhere in the house.

Height is the reason this matters for a loft. A gravity fed shower works on the head of water between the tank and the shower head, and a relocated tank a metre above a loft en suite gives you almost none. That is why loft bathrooms are usually specified with a pump or on an unvented system, and why the decision is worth making deliberately at design stage rather than defaulting to whatever is cheapest on the day.

If the tanks are staying, the platform that carries them has to be designed, because a full storage tank is a serious weight and the ceiling joists it was sitting on are no longer the only consideration.

Hip to Gable Loft Conversions in the Colchester area
Fig. 23
Chapter 23

The en suite: soil route and extract

Getting a 110mm pipe from the top of the house to the drain is a route that has to be found, not assumed.

Almost every hip to gable with a dormer includes an en suite, and the soil connection is the detail that decides where it goes.

The options are a new internal stack, which usually boxes into the corner of a bedroom below and then into a cupboard or the corner of the hall, connecting to the existing drainage at ground level. Or a new external stack on the rear elevation, which is simpler to build and harder to look at, and which on a side elevation raises the same visual questions the gable does. Or connecting into the existing soil stack, which is neat where the geometry allows it and the existing pipe has capacity.

A macerator is the fallback. It works, it is quiet enough now, and it cannot serve as the only WC in the dwelling. It is a compromise rather than a first choice and it should be described as one.

The waste and vent arrangement needs designing rather than improvising: the stack needs venting, either to open air above the roof or through an air admittance valve in an accessible position, and branch connections have length and fall limits.

Extract ventilation from a loft bathroom must reach outside air, which usually means a tile vent or a duct through the dormer cheek. The duct itself has to be insulated where it crosses cold space, or the warm wet air condenses inside it on the way out and the water runs back down into the room. That is a five minute detail at first fix and a recurring complaint if it is missed.

Chapter 24

What a hip to gable costs

Indicative ranges, current at the review date below, and not a quotation.

Scheme Typical range per m² Notes
Hip to gable, rooflights only £1,600 to £2,100 Cut roof, good head height already
Hip to gable plus rear dormer £1,700 to £2,400 The standard 1930s semi scheme
Hip to gable, dormer and en suite £1,900 to £2,600 Soil route and pumped or unvented supply
Trussed rafter roof, same scheme £2,100 to £2,800 New structure before anything is removed
Beam over garage or wide opening Added item Priced separately once the engineer has sized it

That includes: scaffold and temporary weather protection, stripping and setting aside the hip covering, the new gable masonry with cavity work and restraint straps, ridge and purlin alterations, new rafters, tiling and verge detail, structural steels and the new floor, the staircase, fire doors and the protected stairwell works, dormer construction and weathering where included, insulation, rooflights and windows, plastering, first and second fix carpentry, electrics and plumbing to a standard specification, and making good.

It excludes: VAT, en suite sanitaryware and tiling, fitted wardrobes, floor coverings, decoration, professional fees for drawings and structural calculations, planning or certificate fees and Building Control fees, party wall surveyor fees where a neighbour dissents, trial holes and any resulting foundation work, asbestos removal where it is found, and anything that could not be seen before the roof was opened.

The variables that move the number most are whether the roof is cut or trussed, what sits in the flank wall below the gable, how much fire protection the existing staircase needs, and whether there is an en suite. Two houses on the same street can differ by a five figure sum on those four points alone, which is why quoting this job from photographs is not something we do.

Hip to Gable Loft Conversions in the Colchester area
Fig. 25
Chapter 25

How long it takes, and living through it

Eight to twelve weeks on site, plus whatever the front end takes.

Front end first. Where the scheme is permitted development we would apply for a Lawful Development Certificate, which is a determination rather than a decision on merits. Where a full application is needed it is the statutory eight weeks from validation. Building Regulations full plans approval runs alongside. Party wall notices run one or two months depending on the section, and they are shortened only by the adjoining owner consenting in writing, not by everybody being reasonable about it.

On site, a hip to gable with a rear dormer is commonly eight to twelve weeks. Roughly: a week for scaffold and strip out, two to three weeks for the gable, roof structure and steels, two weeks getting it watertight and the dormer formed, a week or so for the staircase, then first fix, plastering, second fix and finishing.

The character of the disruption is different from an extension. Most of it happens above you, which sounds better than it is, because for a period the end of your roof is open under temporary sheeting and that is loud in rain and alarming in wind even when it is entirely secure. Plan for that fortnight rather than being surprised by it.

The genuinely intrusive phase is the staircase, because it happens inside the house. The first floor landing becomes a building site for a week or so, fire doors go onto rooms you are living in, and dust from the stairwell works travels further than anyone expects. Protection is our job rather than yours.

Most families stay throughout. The bathroom keeps working, the kitchen keeps working, and the noise is concentrated in the structural weeks rather than spread across the whole programme.

Chapter 26

Which Colchester housing this suits

The roof type decides it, and around here the roof type follows the decade closely.

Lexden has a great deal of interwar and 1930s hipped housing, both semi-detached and detached, on generous plots with the space to work. It also has a conservation area covering part of it, which switches off permitted development for roof additions entirely within that boundary. Two houses a few hundred metres apart can be on completely different routes, so the boundary is the first thing to check.

Prettygate is largely 1930s through to post-war, and much of the older part is hipped semis with cut roofs and workable head height. This is the classic hip to gable house and the classic hip to gable street, and the symmetry question is a live one on the roads where nothing has been altered yet.

Shrub End and the older parts of Old Heath and Monkwick are mixed. Pre-1960s stock is generally cut roof and convertible. Later phases move to trussed rafters and shallower pitches, and the job changes character with them.

Mile End and Braiswick hold interwar detached and semi-detached houses where a hip to gable frequently produces the largest gain of any option, because the roofs are wide and the hips are eating a lot.

Stanway, Myland and Highwoods are mostly 1980s onwards. Trussed rafters, shallow pitches, and a real chance that permitted development rights were removed by condition on the estate permission. Possible, but check both things before you get attached to the idea.

Villages including Dedham, Wivenhoe, Boxted, West Bergholt and Great Horkesley range from straightforward to genuinely constrained, with conservation areas, the Dedham Vale National Landscape and listed buildings all in play. Outside the city boundary the application and the Building Control notification go to the relevant district authority rather than to Colchester.

Hip to Gable Loft Conversions in the Colchester area
Fig. 27
Chapter 27

Defects we find on gables built by somebody else

The same handful of things, and most of them are invisible once it is plastered.

A gable built over an existing opening with no new lintel or an undersized one, showing up as a stepped crack from the corner of a side window within a couple of winters.

Beam ends bedded straight onto old masonry with no padstone, which crushes locally and drops the beam a few millimetres, which is enough to crack everything above it.

Missing or badly fixed lateral restraint straps, so the new gable is a tall unrestrained panel doing its own thing in a gale.

Purlins stopped short at the new end rather than extended, leaving the new rafters unsupported at mid span. The roof line tells you: sight along it from the garden and a sag at the gable end is obvious once you know to look.

Cavity not closed at the reveal, or no cavity tray where the new work meets an abutment, producing damp on the inside face of the new wall that gets blamed on condensation.

Insulation stuffed tight into the eaves so the ventilation path is blocked, followed by condensation in the void and black mould at the ceiling edge.

Verge detail done in mortar on a wall that has no gable ladder, so the tiles overhang nothing and the mortar cracks off within a few years.

Brick and mortar that do not match, which cannot be fixed afterwards. Matching 1930s facing brick and getting the mortar colour and joint profile right is a specification decision made before ordering, not a hopeful trip to the merchant.

And the paperwork one: a conversion built with no Building Control involvement, presented as a bedroom, discovered by a buyer’s solicitor. That is a problem with a price and a delay attached to it.

Ready when you are

Tell us what you are planning.

One contract, one contact, and the drawings, the engineer and the Building Control notification are our job rather than yours.

Chapter 28

Questions we get asked

Will a hip to gable give me more head height?

No. The ridge stays exactly where it is, so the maximum height in the room does not change. What changes is how much of the floor has that height above it. If your loft measures under about 2.2 metres from ceiling joist to ridge, squaring the hip off will not solve that on its own and you are looking at a dormer as well, or a different project entirely.

Do I need planning permission for a hip to gable?

Frequently not, if it is within the volume allowance and the house is not in a conservation area, is not listed, is not a flat, has no Article 4 direction over it and had no estate condition removing the rights. Combining it with a rear dormer is what most often takes a scheme over the allowance. We check the position on your address before quoting and we tell you which route we think you are on.

Does my neighbour have to agree?

Not for planning purposes. They can comment on an application and the council will consider what they say, but a neighbour has no veto. Under the Party Wall etc. Act it is different: they have a right to notice, a right to dissent, and a right to appoint a surveyor at your cost. Neither of those is a reason to avoid talking to them early, which remains the most useful thing you can do.

Can I do the gable and add the dormer later?

You can, and occasionally there is a good reason to. Mostly it costs more overall, because you pay twice for scaffold, twice for the roof being opened and twice for living through it. It also means the volume already spent on the gable counts against the dormer later, which can push the second phase into an application when the pair together might have been designed differently.

What happens to my neighbour’s roof where the pair meets?

Nothing, in the sense that the shared roof structure over the party wall is not being altered by squaring off your outer hip. What does touch their property is the floor steel bearing into the party wall, which is section 2 work and needs notice, and any scaffold that has to stand on or oversail their side.

Is a timber framed gable acceptable?

Structurally yes, and it is genuinely lighter, which sometimes solves a foundation question. Visually it depends entirely on the street, because it will normally be finished in tile hanging or render rather than matching brick. On a road of plain brick gables it looks like what it is. Where the original houses already use tile hanging, it can be the better answer.

How much value does it add?

We are builders rather than valuers, so the honest answer is to ask a local agent. What we will say is that a hip to gable with a dormer usually produces a genuine double bedroom with an en suite, and that is a different proposition from a room described as a study. There is also a ceiling price for every street, and on a road of three bedroom houses a fourth bedroom has a limit to what it returns.

Hip to Gable Loft Conversions in the Colchester area
Fig. 29
Chapter 29

How we work

One contract, one contact, and the paperwork is our responsibility rather than yours.

Our team has 25+ years in the trade and comes out to look at it. On a hip to gable that survey means going into the loft, measuring the head height from joist to ridge properly, establishing whether the roof is cut or trussed, looking at what sits in the flank wall below the proposed gable, working out where a compliant staircase can land, and checking what the existing stairwell will need for fire protection.

Most people who call us already have drawings and permission and want a builder to price the work and build it. That is the ordinary job here, and we are glad to work to somebody else’s plans. Where the drawings do not exist yet, we bring in the technician who draws it and the engineer who sizes the gable, the steels and the new floor. We deal with the planning route or the Lawful Development Certificate, we tell you which party wall sections apply and when the notices need serving, and we notify Colchester City Council Building Control and manage the inspections through to your completion certificate.

We will also tell you when the answer is no. A shallow trussed roof with no head height, a flank wall full of openings and nowhere for a staircase to land is a project that costs more than it gives back, and saying so at the survey is cheaper for everyone than finding out at week six.

Probuild Extensions Colchester is the extensions arm of Essex Probuild Ltd, company number 15979928. We carry £2m public liability cover and everything is built to current Building Regulations. We are based in West Bergholt, about three miles north west of Colchester, and we work across the city and roughly thirty miles around it. The survey and the quotation cost nothing.

Last reviewed August 2026. Planning rules and Building Regulations change, and your property may differ, so treat this as a guide rather than advice on your specific job.

Get a quote

Tell us what you are planning.

We will come and look at the property, talk through what is realistic, and put a proper number to it. No obligation, and no pressure afterwards.

  • We bring the drawings, the structural engineer and the Building Control notification. You ring one number.
  • Our team has 25+ years in the trade, and he is the one who turns up.
  • £2m public liability cover in place. Work built to current Building Regulations.
  • Straight answers on what a job depends on, before we talk about what it costs.

Request a quote